這 13 張 = 第 8 章(8-1.0~8-10.0)十大支持活動的「活動 → 產出 → 餵進哪份文件」流程圖,與 essence.html 主題 3「文件對照」直接互補——Phase 1 止血重點素材。
共同 pattern:每個領域的 Assessment 產出 → 餵 Business Case + Charter;Planning 產出(XX Management Plan)→ 餵 Program Management Plan。記住這兩條金線,13 張圖就背完一半。

| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Change Assessment | Program Change Assessment | → Program Business Case、Program Charter |
| Program Change Management Planning | Program Change Management Plan、Program Change Thresholds | → Program Management Plan |
| Program Change Monitoring and Controlling | Approved Change Requests、Updates to Program Change Log | — |
反射:變更門檻(Thresholds)是規劃階段定的;批准的變更請求 + 變更日誌更新是監控的產出。

| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Communications Assessment | Program Communications Assessment、Communication Needs Initial Assessment | → Stakeholder Engagement Plan、Program Charter |
| Program Comm Mgt Planning | Program Comm. Mgmt. Plan、Communication Requirements | → Program Management Plan、Stakeholder Register |
| Program Communications Management | Program Communications;Program Information Distribution Methods;Program Reporting → Reports | → Customer Feedback Requests、Periodic Reports and Presentations |
反射:溝通評估特別之處——還餵 Stakeholder Engagement Plan(不只 BC/Charter);Reporting 的下游是定期報告與簡報。

(1) 定義階段前段:
| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Initial Cost Estimation | Program Initial Cost Estimate | → Program Business Case、Program Charter |
| Program Cost Estimation | Program Cost Estimates、Program Cost Estimation Assumptions、Component Cost Estimation Guidelines | — |
| Program Financial Framework Establishment | Program Financial Framework、Business Case Updates、Program Comm. Mgmt. Plan Updates、Program SH Plans Updates | — |

(2) 規劃+交付:
| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Financial Management Planning | Program Financial Management Plan、Initial Program Budget、Program Funding Schedules、Component Payment Schedules、Program Operational Costs、Inputs to Program Risk Register、Program Financial Metrics | → Program Management Plan |
| Program Financial Management | Contract Payments、Closed Component Budgets、Program Budget Baseline Updates、Approved Change Requests、Revised EAC、Program Management Plan Updates、Corrective Actions | — |

(3) 預算與收尾:
反射:Initial Cost Estimate 早於 Charter(餵 BC/Charter);預算對組件是約束、組件估算反映回預算;財務收尾兩件招牌產出=結帳報表+關閉的預算。

| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Information Management Assessment | Program Info Mgt Assessment | → Program Business Case、Program Charter |
| Program Information Management Planning | Program Information Management Plan、Program Info Mgt Tools & Templates | → Program Management Plan |
| Program Information Management | Updates to Program Info Repository;子活動:Information Distribution、Program Reporting | — |
| Program Information Archiving and Transition | Inputs to Organizational Archives、Lessons Learned Report to Organizational Governance Bodies | — |
反射:資訊管理的收尾叫 Archiving and Transition(歸檔+移交);經驗教訓報告交給組織治理機構。

| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Procurement Assessment | Program Procurement Mgt Assessment | → Program Business Case、Program Charter |
| Program Procurement Mgt Planning | Program Procurement Standards、Program Procurement Management Plan、Program Budget Updates、Program Financial Plan Updates | → Program Management Plan |
| Program Procurement Management | RFQ/RFP/IFB、Proposal evaluation criteria、Agreements administration plan、Signed agreements;子活動 Program Contract Administration → Performance/Earned Value Reports、Ongoing Progress Reports、Vendor/Contract Performance Reports | — |
| Program Procurement Closure | Contract Closeout Reports、Updates to Lessons Learned、Closed Contracts | — |
反射:RFQ/RFP/IFB 與簽署協議在「管理」階段;合同管理(Contract Administration)出績效/EV 報告;收尾=合同關閉報告+已關閉合同。

| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Quality Assessment | Program Quality Assessment | → Program Business Case、Program Charter |
| Program Quality Management Planning | Program Quality Management Plan | → Program Management Plan |
| Program Quality Assurance and Control | QA:Quality Assurance Audit Findings、Quality Assurance Change Requests;子活動 Program Quality Control → Quality Change Requests、QC Completed Checklists and Inspection Reports、Quality Test Reports or Measurement Results | — |
反射:項目集層級 QA 是主體(Audit 審計=QA 招牌)、QC 多半下沉到組件;QA 出 Audit Findings、QC 出檢查表/測試報告。

| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Resource Requirements Estimation | Program Resource Requirements Estimate | → Program Business Case、Program Charter |
| Program Resource Management Planning | Program Resource Requirements、Program Resource Management Plan | → Program Management Plan |
| Program Resource Management | Program Resource Prioritization Decisions、Updates to Program Resource Mgt Plan;子活動 Resource Interdependency Management → Updates to Program Resource Mgt Plan | — |
| Program Resource Transition | Resources Released to other Organizational Elements | — |
反射:資源收尾叫 Transition——資源釋放回組織其他單位;交付期重點=資源優先序決策+跨組件資源依賴管理。

(1) Risk Management-1:
| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Initial Risk Assessment | Program Initial Risk Assessment | → Program Business Case、Program Initial Cost Estimate、Program Charter、Program Roadmap(4 份!) |
| Program Risk Management Planning | Program Risk Management Plan、Program Risk Register | → Program Management Plan |
| Program Risk Monitoring and Controlling 檢查 4 件事 | ① Program assumptions 仍有效;② 風險狀態變化與趨勢分析(Risk forecasting);③ 風險政策程序被遵循(Risk Audit);④ Cost/Schedule Contingency Reserves 隨風險調整 | — |

(2) Risk Management-2(Monitoring and Controlling 三子活動 + 移交):
| 子活動 | 產出 |
|---|---|
| Program Risk Identification | Updates to Program Risk Register |
| Program Risk Analysis | Proposed Risk Responses、Updates to Program Risk Register、Periodic Risk Reports Showing Threat and Opportunity Trends |
| Program Risk Response Management | Direction To Implement Risk Responses、Program Risk Register Updates、Contingency Reserve & Management Reserve、Change Requests |
| Program Risk Management Transition | Inputs to Other Organizational Risk Registers |
反射:初始風險評估獨家餵 4 份文件(BC+初始成本估算+Charter+Roadmap)——文件對照高頻考點;Analysis 出「建議的應對」、Response Management 才下「執行指令」與動用儲備金;風險移交=餵其他組織風險登記冊。

| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Schedule Assessment | Program Schedule Assessment | → Program Business Case、Program Charter、Program Roadmap(3 份) |
| Program Schedule Management Planning | Program Schedule Management Plan、Program Master Schedule ⇄ Updates to Program Roadmap、Inputs to Program Risk Register | → Program Management Plan |
| Program Schedule Monitoring and Controlling | Update Program Master Schedule、Update Program Risk Register、Update Program Roadmap | — |
反射:進度評估也餵 Roadmap(和風險初評類似);Master Schedule ⇄ Roadmap 雙向同步是招牌考點。

| 活動 | 產出 | 餵進 |
|---|---|---|
| Program Scope Assessment | Program Scope Assessment | → Program Charter(Program Business Case 灰字=弱連結) |
| Program Scope Management Planning | Program Scope Statement、Program Scope Management Plan、Program WBS | → Program Management Plan |
| Program Scope Monitoring and Controlling | updated Program Scope Statement、Dispositions of Requests、Updates to Program Management Plan、Updates to Program WBS | — |
反射:範圍規劃三件套=Scope Statement+Scope Mgmt Plan+Program WBS;監控產出有「請求的處置(Dispositions of Requests)」——範圍變更請求在這裡被處置。